MEP Coordination
The process of coordinating Mechanical (HVAC), Electrical, and Plumbing systems within a building to ensure ducts, conduits, pipes, and cables don't clash with each other or with structural elements.
Why MEP Coordination Is Construction's Hardest Problem
MEP coordination is challenging because it sits at the intersection of three independent design disciplines (mechanical, electrical, plumbing), each designed by a different consultant, each using their own software, and each optimising their own system without full visibility of the others.
The mechanical consultant routes HVAC ducts for optimal airflow. The electrical consultant routes cable trays for shortest runs. The plumbing consultant routes pipes for gravity flow. When all three are overlaid on the same floor plan, they frequently occupy the same space.
On a typical residential high-rise in India, the number of MEP clash points can exceed 200-300 per floor during the initial design phase. Without pre-construction coordination (using BIM or manual overlay drawings), these clashes are discovered when the plumber can't install a pipe because the HVAC duct is already there.
The Cost of On-Site MEP Clashes
When an MEP clash is discovered on site, the resolution sequence is expensive. The site team raises an RFI to the relevant consultant (3-5 day response typical). The consultant proposes a revised routing (which may affect other systems). The revised design is checked against other trades. The approved revision goes back to site. Work that was already done may need demolition and reinstallation.
Each on-site clash resolution typically costs 3-7 days and involves multiple trades. On a project where 50-100 clashes are discovered on site (a common number when BIM coordination is skipped), the cumulative delay can reach several months.
MEP Coordination Approaches in Indian Construction
Traditional approach: 2D overlay drawings. The architect manually overlays MEP drawings on the structural plan and identifies obvious conflicts. This catches major clashes (a duct running through a beam) but misses elevation conflicts (a pipe and duct at the same height).
BIM-based approach: 3D coordination. All three MEP systems are modelled in a BIM environment and automated clash detection identifies every conflict - including elevation conflicts invisible in 2D. This catches significantly more clashes but requires investment in BIM capability.
Hybrid approach: Design-phase BIM coordination with construction-phase schedule tracking. BIM resolves clashes before construction. Schedule-linked tracking ensures MEP trades execute in the correct sequence during construction - because even clash-free designs can go wrong if the plumber starts before the electrical conduit is complete.
MEP Coordination and the Construction Schedule
MEP work typically represents 30-40% of a building project's cost and an even higher percentage of coordination complexity. The scheduling of MEP work is where most Indian projects lose time.
The common pattern: structural work proceeds floor by floor with a regular cycle time. MEP rough-in (conduits, sleeves, pipe runs) must happen within the structural formwork cycle. MEP finishing (fixtures, equipment, testing) happens during the finishing phase. The gap between rough-in and finishing can be 6-12 months on a high-rise.
This gap means MEP coordination has two critical windows: during structural (where embedded items must be placed correctly in the first pour - there's no going back) and during finishing (where ceiling-level routing must fit within tight clearances). Missing either window creates expensive rework.
Why this matters in construction
MEP systems occupy the space between the structural frame and the finished ceiling. In a typical floor-to-floor height of 3.0-3.2 metres, the MEP zone might be only 600-800mm. Into this space go: HVAC ducts, sprinkler pipes, electrical cable trays, plumbing waste lines, drainage vents, and fire alarm conduits. When these systems are designed independently by different consultants, clashes are inevitable. Every clash resolved on site costs 5-10x what it would cost to resolve on a drawing.
Related terms
Building Information Modeling (BIM)
planningA digital 3D model of a building that contains not just geometry but data - material specifications, cost information, scheduling data, MEP routing, and structural details - enabling coordination and clash detection before construction begins.
Request for Information (RFI)
collaborationA formal question from the contractor or site team to the design team, seeking clarification on drawings, specifications, or scope - essential when construction details are ambiguous or conflicting.
Commissioning
executionThe systematic process of testing, verifying, and documenting that all building systems - HVAC, electrical, plumbing, fire safety, lifts, DG sets - work as designed and meet performance specifications before handover.
How Buildrun Intelligence handles this
Buildrun tracks MEP activities within the construction schedule at the room and zone level, so coordination delays between trades are visible as schedule impacts - not just design issues filed in an RFI register.
